BSI PD IEC TS 63042-302:2021
$198.66
UHV AC transmission systems – Commissioning
Published By | Publication Date | Number of Pages |
BSI | 2021 | 60 |
This part of IEC 63042 applies to the commissioning of UHV AC transmission systems.
It mainly specifies the test purposes, test items, test preconditions, test methods and test acceptance criteria during pre-commissioning and system commissioning. Also, the measurement requirements for system commissioning are specified.
PDF Catalog
PDF Pages | PDF Title |
---|---|
2 | undefined |
4 | CONTENTS |
7 | FOREWORD |
9 | INTRODUCTION |
10 | 1 Scope 2 Normative references 3 Terms and definitions |
11 | 4 General 4.1 Requirements 4.2 Main purpose |
12 | 4.3 General structure of commissioning 4.4 Scope of application 4.5 Technical preparation of system commissioning Figures Figure 1 – General structure of on-site acceptance tests and commissioning Tables Table 1 – Scope of application |
13 | 5 Pre-commissioning 5.1 General 5.2 Combined test 5.2.1 General 5.2.2 Protection and control system test Table 2 – Recommended test items of pre-commissioning |
14 | 5.2.3 Instrument transformer test 5.2.4 Switchgear and transformer test |
15 | 5.2.5 AC and DC power supply system test 5.3 Communication system test 6 System commissioning 6.1 General Table 3 – Recommended test items of system commissioning |
16 | 6.2 Test requirements 6.2.1 General 6.2.2 Energizing test of no-load UHV power transformer 6.2.3 Energizing test of tertiary connected reactor |
17 | 6.2.4 Energizing test of tertiary connected capacitor |
18 | 6.2.5 Energizing test of UHV busbar shunt reactor 6.2.6 Energizing test of UHV busbar |
19 | 6.2.7 Energizing test of no-load UHV transmission line |
20 | 6.2.8 Loop closing (interconnecting)/opening (splitting) test |
21 | 7 Measurement in system commissioning 7.1 General 7.2 Measurement requirements 7.2.1 General 7.2.2 Transient voltage and current measurement Table 4 – Recommended measurement items of system commissioning |
22 | 7.2.3 Electric quantity measurement 7.2.4 Relay protection measurement 7.2.5 Harmonic measurement 7.2.6 Sound level measurement of power transformer/shunt reactor |
23 | 7.2.7 Vibration measurement 7.2.8 DGA of power transformer/shunt reactor 7.2.9 Temperature measurement Table 5 – DGA of UHV transformer, UHV reactor and neutral point reactor |
24 | 7.2.10 Power frequency electric and magnetic field measurement of substation and transmission line 7.2.11 Audible noise measurement of substation and transmission line 7.2.12 Radio interference measurement of transmission line 7.2.13 Partial discharge monitoring in GIS/power transformer |
25 | Annex A (informative)Commissioning experiences in China A.1 General A.2 Overview A.3 Regulations A.4 Pre-commissioning |
26 | Table A.1 – Test items for pre-commissioning of UHV AC transmission projects |
28 | A.5 System commissioning A.5.1 General A.5.2 Technical preparations |
29 | A.5.3 Confirmation on preconditions for on-site commissioning A.5.4 System commissioning tests |
30 | Table A.2 – System commissioning tests for UHV AC transmission projects |
33 | Figure A.1 – Circuit for test of UHV transformer with current increasing from zero |
34 | Figure A.2 – Circuit for test of UHV transformer with voltage increasing from zero |
36 | Figure A.3 – Circuit for loop closing (interconnecting)/opening (splitting)test operated by UHV transmission line circuit breakers |
37 | A.6 Measurement in system commissioning A.6.1 General Table A.3 – Measurement items in system commissioningfor UHV AC transmission projects |
38 | A.6.2 Measurement in system commissioning |
41 | Annex B (informative)Commissioning experiences in Japan B.1 Overview B.2 Regulations B.3 Pre-commissioning in Japan B.3.1 General Table B.1 – Pre-commissioning items |
42 | B.3.2 Combined test |
43 | B.3.3 Communication system test |
44 | B.4 System commissioning in Japan B.4.1 General B.4.2 Energizing test Table B.2 – System commissioning items |
45 | B.5 Measurement in system commissioning in Japan B.5.1 General |
46 | B.5.2 Measurement in system commissioning Figure B.1 – Circuit for transient voltage and current measurement Table B.3 – Measurement items in system commissioning |
49 | Figure B.2 – Analysis results of electrostatic induced fieldin the vicinity of bushing above the ground Figure B.3 – Electrostatic induction field intensity distribution |
53 | Annex C (informative)Commissioning experiences in India C.1 Overview |
54 | C.2 Design, testing, installation, transportation and construction Figure C.1 – Basic set-up at Bina 1 200 kV National Test Station |
55 | C.3 On-site acceptance tests C.3.1 General C.3.2 1 200/400 kV, 333 MVA single phase transformers C.3.3 1 200 kV dead tank spring-spring type SF6 circuit-breakers |
56 | C.3.4 1 200 kV double break centre rotating and knee type disconnector C.3.5 1 200 kV capacitive voltage transformers C.3.6 850 kV surge arrestors C.4 Commissioning |
57 | Figure C.2 – Typical variation in voltage over the period of 4 days at Bina1 200 kV National Test Station |
58 | Bibliography |