{"id":111882,"date":"2024-10-18T16:17:55","date_gmt":"2024-10-18T16:17:55","guid":{"rendered":"https:\/\/pdfstandards.shop\/product\/uncategorized\/ieee-c37-242-2013\/"},"modified":"2024-10-24T22:02:57","modified_gmt":"2024-10-24T22:02:57","slug":"ieee-c37-242-2013","status":"publish","type":"product","link":"https:\/\/pdfstandards.shop\/product\/publishers\/ieee\/ieee-c37-242-2013\/","title":{"rendered":"IEEE C37.242 2013"},"content":{"rendered":"
New IEEE Standard – Active. Guidance for synchronization, calibration, testing, and installation of phasor measurement units (PMUs) applied in power systems is provided. The following are addressed in this guide: (a) Considerations for the installation of PMU devices based on application requirements and typical substation electrical bus configurations; (b) Techniques focusing on the overall accuracy and availability of the time synchronization system; (c) Test and calibration procedures for PMUs for laboratory and field applications; (d) Communications testing for connecting PMUs to other devices including Phasor Data Concentrators (PDCs).<\/p>\n
PDF Pages<\/th>\n | PDF Title<\/th>\n<\/tr>\n | ||||||
---|---|---|---|---|---|---|---|
1<\/td>\n | IEEE Std C37.242-2013 Front cover \n <\/td>\n<\/tr>\n | ||||||
3<\/td>\n | Title page \n <\/td>\n<\/tr>\n | ||||||
6<\/td>\n | Notice to users Laws and regulations Copyrights Updating of IEEE documents Errata Patents <\/td>\n<\/tr>\n | ||||||
8<\/td>\n | Participants <\/td>\n<\/tr>\n | ||||||
10<\/td>\n | Introduction <\/td>\n<\/tr>\n | ||||||
11<\/td>\n | Contents <\/td>\n<\/tr>\n | ||||||
13<\/td>\n | Important notice \n 1. Overview 1.1 Scope <\/td>\n<\/tr>\n | ||||||
14<\/td>\n | 1.2 Purpose 2. Normative references 3. Definitions, special terms, acronyms, and abbreviations <\/td>\n<\/tr>\n | ||||||
15<\/td>\n | 3.1 Definitions 3.2 Special terms 3.3 Acronyms and abbreviations <\/td>\n<\/tr>\n | ||||||
16<\/td>\n | 4. Synchronization techniques, accuracy, and availability 4.1 Introduction 4.2 Role of time synchronization in PMUs <\/td>\n<\/tr>\n | ||||||
17<\/td>\n | 4.3 Satellite-based synchronizing sources <\/td>\n<\/tr>\n | ||||||
21<\/td>\n | 4.4 Terrestrial systems <\/td>\n<\/tr>\n | ||||||
22<\/td>\n | 4.5 Synchronization distribution methods 5. Synchrophasor measurement accuracy characterization 5.1 Introduction <\/td>\n<\/tr>\n | ||||||
23<\/td>\n | 5.2 Data accuracy characterization <\/td>\n<\/tr>\n | ||||||
24<\/td>\n | 5.3 Data accuracy <\/td>\n<\/tr>\n | ||||||
25<\/td>\n | 5.4 Characterization of instrumentation channels <\/td>\n<\/tr>\n | ||||||
26<\/td>\n | 5.5 Characterization of GPS-synchronized measurement devices (PMUs) 5.6 GPS-synchronized equipment reliability <\/td>\n<\/tr>\n | ||||||
27<\/td>\n | 6. PMU installation, commissioning, and maintenance 6.1 Preface 6.2 Overview <\/td>\n<\/tr>\n | ||||||
28<\/td>\n | 6.3 Pre-installation procedures <\/td>\n<\/tr>\n | ||||||
32<\/td>\n | 6.4 Analog and digital input <\/td>\n<\/tr>\n | ||||||
33<\/td>\n | 6.5 Power input 6.6 Communications <\/td>\n<\/tr>\n | ||||||
36<\/td>\n | 6.7 Summary of design considerations <\/td>\n<\/tr>\n | ||||||
37<\/td>\n | 6.8 Pre-installation tests 6.9 Verification of end-to-end calibration <\/td>\n<\/tr>\n | ||||||
40<\/td>\n | 6.10 Communications operation <\/td>\n<\/tr>\n | ||||||
41<\/td>\n | 6.11 Record keeping 7. Testing and calibration 7.1 Overview 7.2 Objective of testing <\/td>\n<\/tr>\n | ||||||
42<\/td>\n | 7.3 Types of tests <\/td>\n<\/tr>\n | ||||||
46<\/td>\n | 7.4 Test equipment <\/td>\n<\/tr>\n | ||||||
52<\/td>\n | 7.5 Methods for performing the tests <\/td>\n<\/tr>\n | ||||||
66<\/td>\n | 7.6 Synchrophasor message format <\/td>\n<\/tr>\n | ||||||
67<\/td>\n | 7.7 Final comments <\/td>\n<\/tr>\n | ||||||
68<\/td>\n | Annex A (informative) \nBibliography <\/td>\n<\/tr>\n | ||||||
72<\/td>\n | Annex B (informative) \nResponses of the reference signal processing model to test signals B.1 General B.2 Introduction to the graphs B.3 Response of the model to steady-state test signals <\/td>\n<\/tr>\n | ||||||
77<\/td>\n | B.4 Response to dynamic input signal tests <\/td>\n<\/tr>\n | ||||||
91<\/td>\n | B.5 Synchrophasor TIMEBASE and TVE <\/td>\n<\/tr>\n | ||||||
92<\/td>\n | Annex C (informative) \nEffects of signal channels C.1 Introduction <\/td>\n<\/tr>\n | ||||||
93<\/td>\n | C.2 Instrument transformer standards <\/td>\n<\/tr>\n | ||||||
94<\/td>\n | C.3 Measured results on instrument transformers <\/td>\n<\/tr>\n | ||||||
96<\/td>\n | C.4 Conclusions <\/td>\n<\/tr>\n | ||||||
97<\/td>\n | Annex D (informative) Examples of instrumentation channel impact on accuracy using approximate models D.1 General D.2 Description of typical instrumentation channels <\/td>\n<\/tr>\n | ||||||
98<\/td>\n | D.3 Potential transformer instrumentation channel error <\/td>\n<\/tr>\n | ||||||
100<\/td>\n | D.4 Current transformer instrumentation channel error <\/td>\n<\/tr>\n | ||||||
102<\/td>\n | D.5 CCVT instrumentation channel error <\/td>\n<\/tr>\n | ||||||
107<\/td>\n | Annex E (informative) \nExample of commissioning tests and measurements <\/td>\n<\/tr>\n<\/table>\n","protected":false},"excerpt":{"rendered":" IEEE Guide for Synchronization, Calibration, Testing, and Installation of Phasor Measurement Units (PMUs) for Power System Protection and Control<\/b><\/p>\n |